Site visit set I girders

Image
10:50am- Bearing pad and end Bents. 11:09am- Delivery of I girders and setting them in place. 1:33pm- Bolting diaphragms in place 2:24pm- Setting deck panels. Starting at the North approach. 3:12pm- Continue to place Deck panels. 4:14pm- Finished product for the day.

Site visit, Poured Bent 1 Cap

Image
 Contractor was ready to pour Bent 1 Cap when I arrived at 9:30. Concrete was an hour and ten minutes late. dispatch had not sent out truck when Joe told them.  Concrete arrived at 11:13, I tested the concrete: Slump 1"-3" after adding 20 Gal water, Air 6%, Temp 74°  Finished pour at 1:05, Girders are scheduled for Tuesday at 11

Site visit, Poured Bent 2 Cap

Image
 Contractor was ready to Pour Bent 2 cap when I arrived, Concrete to arrive at 10. First truck arrived at 10:36, I tested concrete: Slump 4", Air 5.5%, Temp 68°. Made three cylinders, pour went good. Finished pour at 12:30.

Site visit, Drove Bent 1 Piling

Image
Contractor drove all of Bent 1 piling yesterday, one pile needed to be welded on to finish driving. Contractor welded on a piece to finish driving pile.