Site visit, Poured Bent 1 Cap

 Contractor was ready to pour Bent 1 Cap when I arrived at 9:30. Concrete was an hour and ten minutes late. dispatch had not sent out truck when Joe told them.
 Concrete arrived at 11:13, I tested the concrete: Slump 1"-3" after adding 20 Gal water, Air 6%, Temp 74°









 Finished pour at 1:05, Girders are scheduled for Tuesday at 11